EPLAN Electrical Panels Builder Examples
A collection of practical examples and case studies demonstrating the application of EPLAN P8 for electrical panel builders, including real-world scenarios, design considerations, and best practices for panel layout, component selection, and documentation.
EPLAN Electrical Panels Builder Examples
EPLAN P8 for Electrical Panel Builders: Installation Site vs Location Designation
Real-World Panel Builder Scenarios
SCENARIO 1: Multi-Panel Industrial Control System
Project: Automotive Manufacturing Plant
Installation Site (++): Main Assembly Plant Building 3
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
++ Main Assembly Plant Building 3
+ Welding Station 1 - Control Cabinet (MCC-W1)
├─ Main Motor Starter (75 kW)
├─ Safety Relay Module
├─ PLC Controller
└─ Emergency Stop Circuit
+ Welding Station 2 - Control Cabinet (MCC-W2)
├─ Main Motor Starter (75 kW)
├─ Cooling Fan Controller
└─ Pressure Monitoring
+ Assembly Line 1 - Power Distribution Panel (PDP-A1)
├─ Incoming 63A Breaker
├─ 4× 32A Branch Breakers
└─ RCD Protection 300mA
+ Assembly Line 2 - Power Distribution Panel (PDP-A2)
├─ Incoming 63A Breaker
├─ 4× 32A Branch Breakers
└─ RCD Protection 300mA
+ Electrical Room B3-301 - Main MCC Panel
├─ Main 250A Breaker
├─ Transformer Secondary Disconnector
├─ Load Sharing Module
└─ Power Factor Correction
+ Quality Control Room - Testing Panel (QC-TEST)
├─ Safety Interlock
├─ Test Circuit 1-6 (30A each)
└─ Data Logger Interface
EPLAN P8 Designations Generated
1
2
3
4
++Main Assembly Plant Building 3 + Welding Station 1 = Motor Starter 75kW & Schematic
++Main Assembly Plant Building 3 + Welding Station 1 = Safety Relay Module & Schematic
++Main Assembly Plant Building 3 + Assembly Line 1 = Main Breaker 63A & Single Line
++Main Assembly Plant Building 3 + Electrical Room B3-301 = MCC Distribution & Technical Data
Panel Builder Data Sheet Format
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
PROJECT: Automotive Assembly Line - Building 3
PANEL DESIGNATION: ++Main Assembly Plant Building 3
LOCATION-BY-LOCATION BREAKDOWN:
┌─────────────────────────────────────────────────────────────────┐
│ LOCATION: Welding Station 1 - Control Cabinet (MCC-W1) │
├─────────────────────────────────────────────────────────────────┤
│ Cabinet Size: 2000×800×600 mm │
│ Main Supply: 3Ph 400V, 63A, TN-S │
│ Load: 75 kW + auxiliary circuits │
│ Component Count: │
│ - Main Contactor: 1× AF96 (75kW @ 400V) │
│ - Overload Relay: 1× NZM100 (63A setting) │
│ - Aux Relay: 1× CR420 (dual channel safety) │
│ - E-Stop: 1× AC23Z (mushroom head) │
│ - Terminal Blocks: 80-pin arrangement │
│ Wiring Gauge: 16mm² (main), 2.5mm² (control) │
│ Assembly Time: 16 hours │
│ Test Point: TP1, TP2, TP3 (voltage, current, earth) │
└─────────────────────────────────────────────────────────────────┘
┌─────────────────────────────────────────────────────────────────┐
│ LOCATION: Assembly Line 1 - Power Distribution Panel (PDP-A1) │
├─────────────────────────────────────────────────────────────────┤
│ Cabinet Size: 1200×800×400 mm │
│ Main Supply: 3Ph 400V, 63A, TN-S │
│ Branch Circuits: 4 × 32A (industrial sockets) │
│ Component Count: │
│ - Main Breaker: 1× C63 (63A curve) │
│ - Branch Breakers: 4× C32 (32A curve) │
│ - RCD Module: 1× A300/30 (dual channel) │
│ - DIN Rail: 90 mm × 3 sections │
│ - Cable Glands: 6 (metric M25, M20) │
│ Assembly Time: 8 hours │
│ Field Installation: Wall-mounted, 1.5m height │
└─────────────────────────────────────────────────────────────────┘
┌─────────────────────────────────────────────────────────────────┐
│ LOCATION: Electrical Room B3-301 - Main MCC Panel │
├─────────────────────────────────────────────────────────────────┤
│ Cabinet Size: 2400×1200×800 mm (floor-standing) │
│ Main Supply: 3Ph 400V, 250A (from transformer secondary) │
│ Total Outgoing: 6 × 125A circuits │
│ Load: 350 kW continuous + transient surges │
│ Component Count: │
│ - Main Disconnect: 1× OT250D3 (250A isolator) │
│ - Main Breaker: 1× NM250H (250A selective) │
│ - Outgoing MCBs: 6× NM125H (125A each) │
│ - Transformer Secondary: 1× disconnect switch │
│ - Busbar: 160A × 3 sections (copper, 10mm²) │
│ - PFC Capacitor: 1× 25 kVAr (400V) │
│ - Temperature Monitor: 1× TMD23 (earth fault) │
│ Assembly Time: 24 hours │
│ Testing: 3-phase voltage check, insulation test (500V DC) │
└─────────────────────────────────────────────────────────────────┘
SCENARIO 2: Food & Beverage Processing Plant
Project: Bottling Line with Multiple Control Zones
Installation Site (++): Processing Plant South Wing
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
++ Processing Plant South Wing
+ Filling Machine Area - Motor Control Cabinet (MCC-FM)
├─ Main Pump Motor (45 kW, IE3)
├─ Secondary Pump Motor (22 kW, IE3)
├─ Conveyor Drive (11 kW)
├─ Temperature Controller
├─ Pressure Transducer Interface
└─ Emergency Stop Interlocks
+ Labeling Station - Control Panel (CP-LABEL)
├─ Labeling Motor (7.5 kW)
├─ Pneumatic Solenoid Valves (6 circuits)
├─ Vision System Interface (24VDC)
└─ Barcode Scanner Connection
+ Capping & Sealing - Combined Panel (CP-CAP-SEAL)
├─ Capping Motor (5.5 kW)
├─ Sealing Motor (3 kW)
├─ Heater Controller (9 kW resistive)
└─ Position Sensors
+ Quality Control Inspection - Testing Panel (QC-INS)
├─ Optical Scanner PSU
├─ Weight Checker PSU
├─ Data Logger (24VDC powered)
└─ Reject Gate Solenoid
+ Packaging Area - Power Distribution (PDP-PKG)
├─ Main Supply 125A
├─ 6× Branch Circuits 32A (to packaging machines)
├─ Pneumatic Compressor Contactor (15 kW)
└─ Compressed Air Dryer (3 kW)
+ Cleanroom Interface - Isolation Transformer Panel (ISO-CLEAN)
├─ Isolation Transformer 63 kVA (1:1)
├─ Equipotential Bonding
└─ 4× Segregated Circuits to clean area
+ Utility Room SR-101 - Transformer & Distribution
├─ Main Transformer 250 kVA (20kV/400V)
├─ Primary Switching (HV)
├─ Secondary Distribution (250A)
└─ Metering & Monitoring Module
Panel Builder Electrical Analysis
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
INSTALLATION SITE: Processing Plant South Wing
TOTAL CONNECTED LOAD: 168.5 kW
DEMAND FACTOR: 0.75 (simultaneous operation unlikely)
DESIGN LOAD: 126.4 kW
REQUIRED SUPPLY: 250A @ 400V TN-S
LOCATION-BY-LOCATION LOAD BREAKDOWN:
┌──────────────────────────────────────────────────────────┐
│ LOCATION: Filling Machine Area (MCC-FM) │
├──────────────────────────────────────────────────────────┤
│ Connected Load: 45 + 22 + 11 = 78 kW │
│ Diversity Factor: 0.85 (motors rarely run simultaneously)│
│ Demand Load: 66.3 kW │
│ Current @ 400V: I = 66300/(1.73×400×0.92) = 104.2A │
│ Supply Circuit Breaker: 125A (Type C) │
│ Cable: 4×25mm² + 25mm² PE (voltage drop: 2.1%) │
│ Installation Distance: 85m from main panel │
│ Feeder Conduit: φ50mm PVC (underground) │
│ Soft Starter Required: YES (45 kW motor, soft start) │
│ VFD Required: NO (fixed speed operations) │
│ Harmonic Filters: YES (IE3 motors) │
└──────────────────────────────────────────────────────────┘
┌──────────────────────────────────────────────────────────┐
│ LOCATION: Labeling Station (CP-LABEL) │
├──────────────────────────────────────────────────────────┤
│ Connected Load: 7.5 + 0.5 (solenoids) = 8 kW │
│ Demand Load: 8 kW (rarely simultaneous) │
│ Current @ 400V: I = 8000/(1.73×400×0.95) = 12.2A │
│ Supply Circuit Breaker: 32A (Type C) │
│ Cable: 4×4mm² + 4mm² PE (voltage drop: 1.8%) │
│ Installation Distance: 35m from main panel │
│ 24VDC Auxiliary PSU: 480W (integrated) │
│ UPS Backup Required: NO │
└──────────────────────────────────────────────────────────┘
┌──────────────────────────────────────────────────────────┐
│ LOCATION: Capping & Sealing (CP-CAP-SEAL) │
├──────────────────────────────────────────────────────────┤
│ Connected Load: 5.5 + 3 + 9 = 17.5 kW │
│ Demand Load: 15.75 kW │
│ Current @ 400V: I = 15750/(1.73×400×0.93) = 24.4A │
│ Supply Circuit Breaker: 32A (Type B - shorter delay) │
│ Cable: 4×6mm² + 6mm² PE (voltage drop: 2.3%) │
│ Installation Distance: 42m from main panel │
│ Special: Heater inrush monitored (9 kW resistive) │
│ Contactor: AF38 dual main contactors │
└──────────────────────────────────────────────────────────┘
TOTAL SITE DEMAND: 126.4 kW → 250A Supply Adequate ✓
SPARE CAPACITY: ~25% for future expansion
SUPPLY TRANSFORMER: 250 kVA (typical for this load)
Cable Routing Diagram (Electrical Engineering Data)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
Main Transformer (Utility Room SR-101)
↓ (250A, 3Ph 400V TN-S)
├→ [Main MCC @ Electrical Room]
│
├→ [MCC-FM @ Filling Machine] (125A, 85m, 4×25mm²+PE)
│ ├─ Motor M1: 45 kW (soft start, contactor AF96)
│ ├─ Motor M2: 22 kW (direct, contactor AF45)
│ └─ Motor M3: 11 kW (direct, contactor AF30)
│
├→ [CP-LABEL @ Labeling Station] (32A, 35m, 4×4mm²+PE)
│ ├─ Motor M4: 7.5 kW (direct)
│ └─ 24VDC PSU: 480W (for solenoids & vision)
│
├→ [CP-CAP-SEAL] (32A, 42m, 4×6mm²+PE)
│ ├─ Motor M5: 5.5 kW (direct)
│ ├─ Motor M6: 3 kW (direct)
│ └─ Heater: 9 kW resistive (dual contactors AF38)
│
├→ [QC-INS @ Quality Control] (16A, 28m, 4×2.5mm²+PE)
│ └─ All 24VDC PSU powered (optical scanner, weight check)
│
└→ [PDP-PKG @ Packaging] (63A, 52m, 4×16mm²+PE)
├─ Branch 1-6: 32A each (to packaging machines)
├─ Compressor: 15 kW (contactor AF46)
└─ Air Dryer: 3 kW (direct)
TOTAL CABLE LENGTHS: ~282m of armored cable required
CONDUIT SYSTEM: φ50mm main, φ32mm branches
EARTHING: PME supplementary bonding at each panel location
SCENARIO 3: Data Center Power Distribution
Project: Enterprise Data Center Facility
Installation Site (++): Data Center Building West
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
++ Data Center Building West
+ Server Room W-101 (Ground Floor) - PDU Bank 1
├─ Main Disconnect 250A
├─ 4× 63A Branch PDUs (each powers 24 rack units)
├─ Monitoring & Control Module
└─ Emergency Shutdown Station
+ Server Room W-102 (Ground Floor) - PDU Bank 2
├─ Main Disconnect 250A
├─ 4× 63A Branch PDUs
├─ Temperature & Humidity Monitoring
└─ Access Control Interface
+ Server Room W-201 (First Floor) - PDU Bank 3
├─ Main Disconnect 200A
├─ 3× 63A Branch PDUs
└─ Network Tap Integration
+ Cooling Plant Room - Chiller & Pump Control
├─ Main Chiller Motor (45 kW, frequency controlled)
├─ Backup Chiller Motor (45 kW standby)
├─ Circulation Pumps (2× 11 kW)
├─ Temperature Sensor Interface (RTD/PT100)
└─ Alarm & Shutdown Logic
+ UPS Battery Room - DC Distribution & Charging
├─ Main Battery Charger (24V, 2000A capable)
├─ Battery String Monitoring (cell-level voltage)
├─ DC-DC Converters (multiple redundant)
└─ System Monitoring & Logging
+ Main Electrical Room - Utility Interface & Metering
├─ Transformer Secondary Disconnect (HV isolation)
├─ Main Metering Cabinet (revenue grade)
├─ Power Distribution Unit (PDU) main
├─ RCD & Surge Protection Module
└─ Remote Monitoring Interface (SNMP/Modbus)
+ Generator Room - Backup Power System
├─ Diesel Generator Controller (400 kVA)
├─ Automatic Transfer Switch (ATS) 630A
├─ Fuel Level & Temperature Monitoring
└─ Load Shedding Relay Logic
+ Security & Monitoring Room - Control Systems
├─ Access Control PSU (24VDC, 10A)
├─ CCTV System PSU (24VAC)
├─ Fire Alarm Panel Interface
└─ Environmental Monitoring (24VDC)
Critical Electrical Data for Panel Builder
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
INSTALLATION SITE: Data Center Building West
TOTAL INSTALLED CAPACITY: 1,600 kVA (transformer sized)
TYPICAL LOAD: 800 kW (50% utilization baseline)
PEAK LOAD: 1,200 kW (80% utilization maximum)
DESIGN REDUNDANCY: N+1 (dual supply feeders from utility)
LOCATION POWER BUDGETS:
┌──────────────────────────────────────────────────────────┐
│ LOCATION: Server Room W-101 (PDU Bank 1) │
├──────────────────────────────────────────────────────────┤
│ Capacity: 4 × 63A circuits = 252A @ 400V = 174.5 kW │
│ Current Usage: ~120 kW (69% utilization) │
│ Monitored Power: Yes (metered at each PDU) │
│ Redundancy: Dual-fed from separate MPD main breakers │
│ Current @ rated load: 252A (split across 4 circuits) │
│ Cable: 4 × (4×25mm² + 25mm² PE) per PDU │
│ Conditioning: Isolation transformer fed (backup power) │
│ Next Expansion: Can upgrade to 315A (4×63A+spare) │
└──────────────────────────────────────────────────────────┘
┌──────────────────────────────────────────────────────────┐
│ LOCATION: Cooling Plant Room │
├──────────────────────────────────────────────────────────┤
│ Connected Load: 45 + 45 + 11 + 11 = 112 kW │
│ Demand Load: 90 kW (chiller + 1 pump running) │
│ Current @ 400V: I = 90000/(1.73×400×0.92) = 141A │
│ Supply Breaker: 160A (selective curve C) │
│ Cable: 4×35mm² + 35mm² PE (voltage drop: 1.2% @ 250m) │
│ VFD Required: YES (main chiller, 45 kW, variable load) │
│ Soft Starter: NO (fixed backup chiller) │
│ Motor Thermistors: All motors fitted (protection) │
│ Special: Synchronous start between primary & backup │
│ Load-Sharing: Intelligent control (HVAC system) │
└──────────────────────────────────────────────────────────┘
┌──────────────────────────────────────────────────────────┐
│ LOCATION: Main Electrical Room (Central MPD) │
├──────────────────────────────────────────────────────────┤
│ Incoming Supply: Dual 400A feeders from transformer │
│ Main Metering: Revenue-grade (±0.5% accuracy) │
│ Total Switchboard Capacity: 630A main bus │
│ Outgoing Circuits: │
│ - W-101 PDU: 250A (direct feeder) │
│ - W-102 PDU: 250A (direct feeder) │
│ - W-201 PDU: 200A (direct feeder) │
│ - Cooling: 160A (direct feeder) │
│ - Generator ATS: 630A (direct feeder) │
│ - UPS Charger: 125A (direct feeder) │
│ - Security: 32A (direct feeder) │
│ Total Switchboard Capacity: 630A (suitable at N+1 config)|
│ Protection: Selective coordination (TCC curves matching) │
│ Harmonic Filtering: Yes (VFD at cooling) │
│ Surge Protection: Type 1 (building entry) + Type 2 (PDU) │
│ Monitoring: Powermon 6000 (SNMP/Modbus/DNP3) │
│ Component List (Switchboard): │
│ - Main Disconnect: 1× OT630D3 (630A isolator) │
│ - Main Breaker: 1× NM630N (630A, selective) │
│ - Metering Module: 1× MT600 (3-phase 600A) │
│ - Outgoing MCBs: 8 × NM250-400H (250-400A range) │
│ - RCD Module: 1× MA300 (300mA dual channel) │
│ - Busbar: 400A × 4 vertical sections (copper) │
│ - Terminal Blocks: 160-pin industrial grade │
│ - Condition Monitoring: Thermal camera ports │
│ Assembly Size: 2400×2000×1000 mm (floor-standing) │
│ Assembly Time: 48 hours (critical infrastructure) │
└──────────────────────────────────────────────────────────┘
┌──────────────────────────────────────────────────────────┐
│ LOCATION: Generator Room (Backup Power) │
├──────────────────────────────────────────────────────────┤
│ Generator Size: 400 kVA (standby), 1500 rpm │
│ Fuel Type: Diesel (on-site storage) │
│ Current @ full load: 400000/692 = 578A @ 400V 3Ph │
│ ATS (Automatic Transfer Switch): 630A │
│ ATS Type: STS-6300 (make-before-break, 3-phase) │
│ Transfer Time: <100ms (UPS bridge load) │
│ ATS Contactors: 2× AF900 (dual-source changeover) │
│ Utility Feed Disconnect: Main ATS isolation │
│ Generator Control Panel: │
│ - Engine Controller (AMF module) │
│ - Frequency Monitor: 48-52 Hz acceptable │
│ - Voltage Monitor: 380-420V acceptable │
│ - Load Shedding Logic: 4-tier (non-critical first) │
│ - Fuel Level Indicator & Gauge │
│ - Oil Temperature & Pressure Monitoring │
│ - Exhaust Temperature Monitor │
│ Fuel Supply: 5000L on-site (16-hour runtime @ 75% load) │
│ Emission: Meets Stage 3B regulations │
│ Testing: Monthly test-run (30 min no-load) │
│ Documentation: Full maintenance log required │
└──────────────────────────────────────────────────────────┘
LOAD PROFILE (24-HOUR):
Time Load Supply Notes
06:00 600 kW Grid Morning startup
09:00 900 kW Grid + UPS Peak business hours
12:00 800 kW Grid Steady-state
18:00 950 kW Grid Evening peak
22:00 500 kW Grid Off-peak reduced
00:00 350 kW Grid Maintenance window
REDUNDANCY VERIFICATION:
✓ Dual feeder system (N+1 for main supply)
✓ Generator backup (8-hour autonomy with fuel load)
✓ UPS system (15-minute battery bridge)
✓ Cooling redundancy (dual chillers, one primary + one standby)
✓ PDU redundancy (each rack has dual-corded PSUs)
SCENARIO 4: Chemical Plant Process Control
Project: Reactant Dosing & Temperature Control System
Installation Site (++): Chemical Plant Building C (East Wing)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
++ Chemical Plant Building C (East Wing)
+ Reactor Control Room 1 - Main Process Panel (CP-REACT-1)
├─ Reactor Heater Circuit 1 (36 kW resistive)
├─ Reactor Heater Circuit 2 (36 kW resistive)
├─ Chiller Motor (22 kW)
├─ Agitator Motor (15 kW)
├─ Dosing Pump Motor (7.5 kW)
├─ Temperature Sensor Interface (PT100 RTD)
├─ Pressure Transducer Circuit (4-20mA)
└─ Safety Interlocks & E-Stop
+ Reactor Control Room 2 - Process Panel (CP-REACT-2)
├─ Reactor Heater Circuit 1 (36 kW resistive)
├─ Reactor Heater Circuit 2 (36 kW resistive)
├─ Chiller Motor (22 kW)
├─ Agitator Motor (15 kW)
├─ Dosing Pump Motor (7.5 kW)
└─ Control Interface & Monitoring
+ Auxiliary Equipment Room - Support Panel (SP-AUX)
├─ Vacuum Pump Motor (11 kW)
├─ Inert Gas Supply Compressor (7.5 kW)
├─ Ventilation Exhaust Fan (5.5 kW)
├─ Fume Hood Supply Fan (3 kW)
└─ Chemical Supply Chiller (5.5 kW)
+ Utility Room C-201 - Main MCC & Distribution
├─ Main Transformer Secondary 400A
├─ Main Distribution Breaker
├─ Outgoing Breakers (to each control area)
├─ Harmonic Filter Module (THD control)
└─ Power Quality Monitor
Electrical Load & Cable Sizing Analysis
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
108
109
110
111
112
113
114
115
116
117
118
119
120
121
122
123
124
125
126
127
128
129
130
131
132
133
134
135
136
137
INSTALLATION SITE: Chemical Plant Building C (East Wing)
TOTAL PROCESS LOAD: 246 kW
DUTY CYCLE: Continuous (24/5 operation)
DESIGN SAFETY MARGIN: 25%
REQUIRED SUPPLY: 315A @ 400V TN-S
LOCATION 1: Reactor Control Room 1 (CP-REACT-1)
────────────────────────────────────────────────
Connected Load: (36+36+22+15+7.5) = 116.5 kW
Diversified Load: 110 kW (heaters 100%, motors 75%)
Current Required: I = 110000/(1.73×400×0.92) = 172A
Supply Breaker: 200A (Curve D for inrush resistance)
Cable Specification: 4×35mm² + 35mm² PE
Distance from Main: 120m (underground conduit)
Voltage Drop Calc: Vd = (2×L×I×R)/1000 = 2×120×172×0.00163/1000 = 0.067V = 0.016% ✓
[Note: 35mm² Cu = 0.00163 Ω/m]
Installation Method: 4-core armored cable in buried conduit φ50mm
Earth Fault Loop: Tested <0.5Ω (measured at site)
Protection: Bi-metal thermal overload + MCB discrimination curve
Temperature Compensation: Heater thermostat ±2°C accuracy
HEATER CIRCUITS (Critical Load Segment):
├─ Heater 1: 36 kW @ 400V = 52A → CB C63 (3-pole)
├─ Heater 2: 36 kW @ 400V = 52A → CB C63 (3-pole)
├─ Cable: 2×6mm² per heater (single phase distributed)
├─ Control: Contactor AF45 + thermal overload NZM45
├─ Contactor coil: 24VDC (from dedicated PSU)
└─ Interlock: Safety relay prevents both heaters ON simultaneously
MOTOR CIRCUITS:
├─ Chiller Motor 22kW: CB C32, Cable 4×10mm²+PE, DOL starting
├─ Agitator Motor 15kW: CB C32, Cable 4×6mm²+PE, DOL starting
├─ Dosing Pump 7.5kW: CB C20, Cable 4×4mm²+PE, DOL starting
MONITORING CIRCUITS (Instrumentation):
├─ PT100 Temperature Sensor: 3-wire, 1.5mm² shielded pair
│ Signal Range: -20 to +150°C (RTD output)
│ Transmitter: DIN-rail mounted, 4-20mA output
│ Cable: Armored shielded pair (EMI immunity)
│ Distance: 35m to sensor (compensation wiring)
│
├─ Pressure Transducer: 0-10 bar → 4-20mA output
│ Mounting: Vessel flange-mounted (IP67 connector)
│ Signal Conditioning: Isolator module (galvanic isolation)
│ Cable: 2-conductor 0.75mm² shielded (50m run)
│
└─ E-Stop Circuit: 24VDC dual-channel safety relay
Safety Rating: PNEU SIL2 Category 3
Relay Type: CR420 (redundant contacts)
Response Time: <10ms
LOCATION 2: Reactor Control Room 2 (CP-REACT-2)
────────────────────────────────────────────────
Configuration: IDENTICAL to CP-REACT-1
Connected Load: 116.5 kW (parallel installation)
Supply Breaker: 200A (independent feed)
Cable: Separate 4×35mm² run (parallel to Reactor 1)
Distance from Main: 115m (separate underground route)
Cross-connection: None (safety-critical separation)
LOCATION 3: Auxiliary Equipment Room (SP-AUX)
────────────────────────────────────────────────
Connected Load: (11+7.5+5.5+3+5.5) = 32.5 kW
Diversified Load: 30 kW (motors 75%, fan 100%, chiller 100%)
Current Required: I = 30000/(1.73×400×0.92) = 47A
Supply Breaker: 63A (Curve C, general purpose)
Cable: 4×10mm² + 10mm² PE
Distance from Main: 85m
Voltage Drop: 0.041V = 0.010% ✓
Installation: Above-ground conduit (machine room area)
Motors: All DOL starting (low-inertia machines)
Fans: Soft-start recommended (reduce stress on building ventilation)
LOCATION 4: Main Utility Room (MCC @ Utility C-201)
────────────────────────────────────────────────────
Incoming Supply: 400A dual feeders from 630kVA transformer
Main Distribution Architecture:
┌─────────────────────────────────────┐
│ Main Transformer Secondary 630kVA │
│ 20kV:400V, 1000A nominal │
└──────────────────┬──────────────────┘
↓
┌──────────────────────┐
│ HV Disconnect (OT80)│ ← 20kV side isolation
│ LV Main Breaker NM1000 (1000A)
└──────────────────────┘
↓
┌──────────────┼──────────────┐
↓ ↓ ↓
[CB-1] [CB-2] [CB-3]
315A Feed [Harmonic [Metering]
to Reactor Filter]
Room 1
↓ ↓ ↓
[CP-REACT-1] [THD <5%] [kWh Meter]
↓ Protection [Power Analyzer]
[200A Outlet]
MAIN SWITCHBOARD COMPONENTS:
├─ Main Isolator: OT630D3 (630A knife switch, HV side)
├─ Main Breaker: NM630H (630A, selective curve)
├─ Metering: MD500 (3-phase, 600A capacity)
├─ Outgoing MCBs:
│ ├─ CB1: NM315H (315A) → CP-REACT-1
│ ├─ CB2: NM315H (315A) → CP-REACT-2
│ ├─ CB3: NM100H (100A) → SP-AUX
│ ├─ CB4: NM63H (63A) → Utility Loads
│ └─ Spare: 2 breakers available
├─ RCD Protection: MA300 (300mA, dual channel)
├─ Harmonic Filter: FLW-25-7-400 (25 kVAr, 7th harmonic)
├─ Power Quality Monitor: Powermon 8000 (web interface)
└─ Busbar: 400A copper × 4 compartments
HARMONIC MITIGATION (Critical):
┌────────────────────────────────────┐
│ THD Source Analysis: │
│ ├─ Heater coils: Minimal (resistive)│
│ ├─ Motors (DOL): 20-30% THD │
│ ├─ Motor soft-starters: 40% THD │
│ └─ Cumulative @ 200A: ~25% THD │
└────────────────────────────────────┘
Mitigation: Fixed harmonic filter (25 kVAr, tuned to 7th harmonic)
Result: THD reduced to <5% (compliance with EN 61000-2-2)
Benefit: Reduced cable heating, longer equipment life
PROTECTION COORDINATION:
Time (ms) Event Action
0 Short circuit occurs All breakers see fault current
1-5 Instantaneous zone Main breaker sees 400A+, trips instantly
5-50 Short delay zone Outgoing breakers see current surge
50-100 Long delay zone Thermal overload elements activate
>100 Thermal overload Motor protection operates (12-16s @ 130%)
TCC (Time-Current Curves) verified for:
✓ Main breaker faster than outgoing breakers
✓ Motor overload slower than branch breaker
✓ All curves coordinated for selective operation
Panel Builder Design Checklist for EPLAN P8
For Each Location, Verify:
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
LOCATION DESIGNATION SETUP:
□ Unique location code assigned (e.g., "CP-REACT-1", "MCC-FM")
□ Physical address documented (building, room, coordinates)
□ Distance to main supply calculated
□ Environmental conditions noted (temp, humidity, hazardous area)
ELECTRICAL LOAD ANALYSIS:
□ Connected load calculated (sum of all devices)
□ Demand load estimated (diversity factors applied)
□ Peak inrush current identified (motor soft-start required?)
□ Voltage drop verified (<3% branch, <5% total)
□ Cable gauge selected & confirmed
□ Protective device ratings calculated
COMPONENT SELECTION:
□ Main breaker rated for full load + margin
□ Branch breakers coordinated for selective operation
□ Cable glands, shrouds, terminal blocks specified
□ Mounting hardware selected (DIN rail vs. busbar)
□ Heatsinks/cooling provisions assessed
DOCUMENTATION GENERATION:
□ Schematic diagram created (functional symbols per IEC 60617)
□ Single-line diagram for distribution (power flow)
□ Cable routing diagram (with conduit sizes)
□ Control circuit details (24VDC PSU, interlocks)
□ BOM (Bill of Materials) extracted from EPLAN database
SAFETY & COMPLIANCE:
□ Earth fault protection (RCD/FI) specified
□ Surge protection (Type 1, 2, 3) installed
□ Harmonic filtering assessed (if VFDs present)
□ Temperature monitoring provisions (thermistor/PT100)
□ Emergency stop circuits interlocked
□ Access to live parts restricted (IP54 minimum)
□ Heat dissipation adequate (thermal load calculation)
TESTING & COMMISSIONING:
□ Insulation test performed (500V DC, >10MΩ)
□ Continuity test on all circuits
□ Phase rotation verified (3-phase systems)
□ Load test at 80% rated current
□ Temperature rise verified (no component >40°C rise)
□ Final sign-off & labeling complete
JSON Data Format for Panel Documentation
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
{
"installationSite": "Chemical Plant Building C (East Wing)",
"designCode": "++CP-BldgC-East",
"locations": [
{
"locationDesignation": "Reactor Control Room 1",
"locationCode": "CP-REACT-1",
"distanceFromMain": {
"value": 120,
"unit": "meters"
},
"connectedLoad": {
"value": 116.5,
"unit": "kW"
},
"diversifiedLoad": {
"value": 110,
"unit": "kW"
},
"supplyBreaker": {
"type": "NM315H",
"ratedCurrent": {
"value": 200,
"unit": "A"
},
"curve": "Type D"
},
"cableSpecification": {
"cores": 4,
"crossSection": {
"value": 35,
"unit": "mm²"
},
"earthing": {
"value": 35,
"unit": "mm²"
},
"voltageDrop": {
"value": 0.016,
"unit": "%"
}
},
"components": [
{
"functionDesignation": "Reactor Heater 1",
"type": "Resistive Heater",
"power": {
"value": 36,
"unit": "kW"
},
"breaker": "C63",
"cable": "2×6mm²"
},
{
"functionDesignation": "Chiller Motor",
"type": "Three-phase Asynchronous Motor",
"power": {
"value": 22,
"unit": "kW"
},
"breaker": "C32",
"cable": "4×10mm²+PE",
"protection": "Direct-On-Line"
},
{
"functionDesignation": "Temperature Sensor Interface",
"type": "PT100 RTD Transmitter",
"signal": "4-20mA",
"cable": "1.5mm² armored shielded pair",
"distance": {
"value": 35,
"unit": "meters"
}
}
]
}
],
"documentGeneration": {
"schematic": "CP-REACT-1-Schematic.pdf",
"singleLine": "CP-REACT-1-SingleLine.pdf",
"cableRouting": "CP-REACT-1-Cabling.dwg",
"bom": "CP-REACT-1-BOM.xlsx"
}
}
Key Takeaways for Panel Builders
- ++ (Installation Site) = Where your panel is located (building, facility)
- + (Location Designation) = Specific room/area (control room, electrical room)
- = (Function Designation) = What the panel does (motor control, power distribution)
- Use this hierarchy to generate documentation, BOMs, and cable lists automatically
- EPLAN P8 exports this structure into Excel, CAD, and electrical reports
- Data-driven design ensures consistency across multi-location projects
This post is licensed under CC BY 4.0 by the author.
